The Underline

Overview
The Underline is transforming the land below Miami’s Metrorail into a world-class, 120-acre linear park, urban trail and public art destination. The full project will span 10-miles that will transform regional mobility and celebrate diversity, culture and lifelong learning. The full project will span 10-miles that will transform regional mobility and celebrate diversity, culture and lifelong learning. Through innovative urban trails and creative programming, the Underline is connecting people to their environment and each other to create a safe, healthy, equitable and sustainable community. The Underline project is a collaboration between the Meg Daly-led 501C3 non-profit organization Friends of the Underline and Miami-Dade County of Department of Transportation & Public Works (DTPW), with additional funding from the Florida Department of Transportation (FDOT), the State of Florida, the City of Miami, and the Miami DDA.
Master Plan Goals
This project is not specifically outlined in the Master Plan.
- 4.0 Create Great Streets and Community Spaces
- 4.3 Enhance Connectivity to Neighborhoods Surrounding Downtown
- 5.1 Rebalance Roadways Towards Transit, Pedestrians and Cyclists
Status
- Phase 1, the ½ mile section from the Miami River to SW 13th St, was completed and opened in February 2021. The first phase is named the "Brickell Backyard."
- Phase 2, from SW 13th St to SW 19th Avenue, is a 2.14-mile segment and is named the "Hammock Trail." Construction began in Fall 2021 and was completed in April of 2024.
- Phase 3, the 7.36-mile segment extends from SW 19th Avenue to its southern terminus at the Dadeland South Metrorail Station. Sections of Phase 3 opened to the public throughout 2026, including five continuous miles celebrated in May 2026 and an additional 1.2-mile southern section opened in July 2026. On November 12, 2026, The Underline celebrated the completion of its full 10-mile corridor with an inauguration event attended by Miami-Dade County Mayor Eileen Higgins, marking a major milestone in the transformation of this urban trail and linear park. While the 10-mile corridor has been celebrated and opened, some remaining station connections and ancillary improvements, particularly around Dadeland South, are expected to continue through April 2027.
- The Miami DDA increased its boundaries to include the Underline in 2019, allocated 1 Ambassador (7 days a week) to patrol the area/participate in events, 1 DET team member (5 days a week) to assist with maintenance, and provided 1 Pit-Stop public bathroom that will be maintained full-time.
- Looking Ahead: With the 10-mile corridor now celebrated and open, The Underline represents a significant investment in Miami-Dade County's public spaces, transportation connectivity, and quality of life. The completed corridor connects eight Metrorail stations and surrounding neighborhoods, encouraging walking, cycling, public transportation, recreation, and community engagement. Remaining station connections and ancillary improvements, particularly around Dadeland South, are expected to continue through April 2027.